Concrete Building (G+M+3) Structural Evaluation

EXISTING CONCRETE BUILDING (G+M+3)

1. Building description

The building under study is located in ---------- on the main road -------- and ------- street. Also, it is worth mentioning that the building had been assigned two different address numbers.

The building consists of ground, a mezzanine, and three typical floors. The ground and mezzanine floors are used as shops. The typical floors are used as workers' accommodation.

The structure is made of conventional concrete slabs supported by beams that transfer the loads to the columns, and the latter transfer the loads to the strata through footings.

Figures 1 to 2 illustrate the building from different angles.

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure 

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

2. Visual inspection

During the physical observation, all floor levels were inspected, considerable areas were exposed and checked, and a general assessment was conducted. Investigation for various signs of deterioration was conducted, such as cracks' patterns, spalling and delamination of concrete, honeycombs, discoloration, etc. Also, a check for excessive deflection and distress, such as flexural and shear cracks, was carried out.

The physical observations made during the inspection are summarized below, and figures from 4 to 9 present part of the visual observation.

 

1.     There is no sufficient offset between the building and the building next to it. Also, the building is attached to the building behind it.

2.     Various temperature and shrinkage cracks were observed all over the building.

3.     Numerous corrosion cracks were observed. Also, a trail of corrosion was noticed.

4.     Concrete cover spalling and exposure of reinforcement was observed in several areas

5.     A lot of exposed reinforcement bars have experienced a size reduction due to corrosion.

6.     Concrete discoloration was detected in many places all over the building.

7.     Concrete delamination and paint peeling were observed all over the building.

8.     Horizontal cracks between concrete beams and slabs with blockwork were observed in various places.

9.     Blockworks horizontal and vertical cracks in various places.

10. Signs of water leakage were observed in many places

11. Trails of humidity and fungi due to water leakage were noticed.

12. The roots of the existing tree; just attached to the column, could adversely affect the column footing

13. Some occupants had improperly demolished parts of the walls to make openings.

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

 structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure
structural engineering,structural,structural evaluation,structural evaluations,structural model evaulation,evaluation,structural analysis,structural assessment,#structural,structural engineer,structural model,structural design,structural survey,structural engienering,structural condition assessment,structure

3. Conducted Tests

   

Tests, mainly and mostly, were conducted on the columns since they are the critical structural element in the building. The following tests were conducted:

 

1.     Carry out ultrasonic Pulse velocity test as per EN 12504-4:2004.

2.     Obtain concrete cores from different locations of the building to assess the physical and mechanical properties of the existing concrete, according to EN 12504-1:2009.

3.     Measure the carbonation depth of concrete elements by using the phenolphthalein indicator according to BS 1881-201:1986 and BS EN 14630.

4.     Extract reinforcement steel sample for a tensile test following ASTM A370 or ISO 15630-1.

 

4. Tests Results

The following shows the results of the tests conducted. Table 1 summarizes the conducted tests' results.

4.1 Ultrasonic Test

The ultrasonic test was conducted on several columns to examine the quality of the concrete in general. Nine columns and one slab were tested. The results values were varying between 1968 m/s and 3324 m/s, which means that concrete condition varies between very poor and questionable conditions.

 

4.2 Compressive strength Test

Ten concrete cores were extracted from the entire building, nine cores from the columns, and one core from the slabs. One of the cores of the columns was shattered during the test, and no result was obtained.

Core compressive strength test results vary between 8.0 MPa and 19.5 MPa for columns. As for the slabs, the compressive strength was 16.5 MPa. Table 2 present the compressive strength results by implementing the standard deviation to calculate the average concrete strength.

 

4.3 Carbonation Test

Carbonation was observed in nine of ten extracted samples and the carbonation depth vary between 0.9 cm to 4.1 cm.

 

4.4 Tensile Test

Two specimens were extracted from columns to know the yield strength of the reinforcement steel used in the structural elements. The yield strength of the deformed bars was 249 and 286 Mpa.


5. Discussion of Tests Results and Visual Inspection

From the physical investigation conducted, the tests' results obtained, and the experience with similar buildings, most of the observed cracks are the expected output due to the building's age, lack of regular and preventive maintenance, and the effect of temperature variation and humidity rate.

Despite the ultrasound tests' results having shown a few intermediate values, yet, the average velocity was found 2557 m/s, which means poor concrete condition. This conclusion was confirmed by the compressive test results obtained, where the average concrete strength was 11.6 MPa.

All tested columns had shown low strength values, and in some tested columns, the values were extremely low, e.g., 8.0 MPa. The low compressive strength of the concrete columns is most probably led to the load of the blockwork walls and/or to redistributing the loads to stronger elements and cause some cracks to occur. Furthermore, the reduction in the area of the reinforcing steel, due to corrosion, with the low yield strength had been adding an adverse effect on the strength of the structural elements.

Also, the finite space between the building and the neighbor building allows for water accumulation and a humid atmosphere during the rainy season, and this adversely affects the concrete element and expedites the deterioration process.

 90% of the carbonation test for the extracted samples had shown carbonation depth vary between 0.9cm to 4.1cm which means the alkanity of concrete in these locations was reduced and the protection of steel bars against corrosion was reduced by oxidation

Due to the existence of the tree just attached the column could adversely affect the column footing by the tree roots. 


6. Conclusion

Based on the current condition of the building, the absence of maintenance, and the obtained tests' results are evidence that the building keeps undergoing further deterioration. The structural condition is considered hazardous, and the safety of the occupants is at risk since the concrete cover in slabs is delaminated in many places and could fall at any moment. Also, many structural and non-structural elements are loaded with unconsidered loads; this excessive load could impair their serviceability.

Based on the above, more than 70% of the structural elements require rehabilitation and strengthening.

End of Report

Hussein Abdeldayem

أكثر من أربعة وعشرون (24) عامًا من الخبرة في مشاريع البناء والتشييد بما يخص تنفيذ واستلام بنود الاعمال المدنية والتشطيبات والتصميم الإنشائي وتقييم الحالة الإنشائية للمباني القائمة ووضع الحلول الإنشائية المناسبة لتحسين حالة المبنى وإعادة تأهيله، ونسعى إلى الاستثمار في اكتساب خبرات تنفيذ الأعمال المدنية والتشطيبات والتميز في مجال العمل والوصول لأكبر مكاسب في أقل وقت.

Post a Comment

Write your comment or inquiry on the topic

Previous Post Next Post

نموذج الاتصال